9/11/25 - Site grading has begun on the south portion of the project. This includes stripping top soil and stockpiling it along with excavating of the ponds. Silt fence is being installed around the perimeter of the project and around wetlands.

9/5/25 - Tree clearing will begin today 9/5/25 and Saturday 9/6/25. Silt fence installation and site grading is scheduled to begin Monday 9/8/25.

8/27/25 - Tree clearing is scheduled to begin on Wednesday 9/3/25. Grading is scheduled to begin Monday 9/8/25.

8/19/25 - Surveyors will be on-site to mark out removals, silt fence, and the road centerline.

8/13/25 - The project is scheduled to begin 9/2/25. The proposed project schedule can be found here Proposed Project Schedule. Note that this is subject to change depending upon weather and Contractor scheduling.

7/29/25 - 2111 Resident Notice - Project Info have been sent out via mail to inform residents of the project.

7/23/25 - The project was awarded to A-1 Excavating LLC at the 7/21/25 City Council Meeting

6/18/25 - Bid Opening will be 7/9/25 at 11:00 AM. Council acceptance of lowest bid is planned for 7/21/25.

6/17/25 - The City Council approved the project to be advertised for contractor's bids.



Approved Plans



 

 
The above information will be maintained as up to date as possible.