155th Avenue from Naples Street to Lexington Avenue upgrade

Lead Engineer: Tom Collins, P.E.
E-mail: tcollins@rfcengineering.com
(763) 862 - 8000

Contractor contact information:
Dresel Contracting
Josh Dresel, President; Office: (651) 257-9469 Cell: (651) 328-1470
Craig Meyer, Project Manager; Office: (651) 257-9469 Cell: (612) 328-1478

3/18/20: Construction is scheduled to commence in April, 2020. A resident notice was sent out today which can also be viewed by clicking Resident Notice.

9/4/19: The City Council awarded the project to Dresel Contracting

8/29/19: Bids will be opened at 10:00am.

8/8/19: Advertisement for Bids were advertised in Star Tribune and on QuestCDN.com.

2/14/19: Surveyors will be on site marking trees and staking/flagging areas to be cleared on Monday, February 18th. The contractor could begin tree clearing work as early as Tuesday, February 19th. A resident notice was sent out today which can also be viewed by clicking Resident Notice.

The tree removal plans can be viewed at Tree Removal Plans.

Tree removal will be completed between February 19th and March 31st. Stump removal will be completed by May 31st.

11/5/18: Construction is scheduled to commence in 2019.


Approved Plans

Projected Schedule

6/16/20: Driveways are scheduled to be paved Wednesday 6/17/20. Top Lift of of paving is scheduled for Friday, 6/19/20. Shouldering and project wrap up to follow (late June, 2020).

7/21/20: Road reconstruction completed. Punch list items such as bituminous driveway corrections and shoulder material corrections waiting to be addressed.



 

 
The above information will be maintained as up to date as possible.